Repair Works Along Quriyat Sur Road
1220
Oman
Ministry of Transport & Communications
Scope of the project consists of the repair and strengthening works along the concerned road after the damaged suffered because of the Gonu and Phet cyclones. The repair and strengthening works concern the entire road and involve structures like culverts and bridge foundations as well as road drainage and protection against scouring.
Design Review and Construction Supervision which include the following:
1) Assist the Employer in Contract Administration and in Contract Management
2) Provide guidance and direction to the Contractor
3) Furnish all necessary ground and topographic data, including setting out of control points
4) Issue the interim payment certificate based on the progress at site and according to the conditions of the contract
5) Review and recommend for approval revision (if any) of Contractor's work schedule
6) Establish standardized Quantity and Quality control programs (Quality Plan)
7) Establish Safety plan
8) Review and approve Contractor's working drawings and temporary works proposals
9) Provide supervision of works to ensure Contractor's compliance with the specs and contractual obligations
10) Notify the Employer about Contractor's claims and provide the Client with the evaluation
11) Prepare variation orders, evaluate request of time extension
12) Keep the Client informed about progress and problems or potential problems
13) Coordination with Local Authorities and Third Parties involved in the works
Roads & Bridge
Supervision
4-Sep-12
On going